Whitehaven Harbour Update.

February 2026.

The problems of the harbour and town of Whitehaven do not appear to be getting any better despite the best efforts of those who care for the place. The work due to be started to rectify the issue of minewater have been postponed due to the findings of one of our helpers. He is a retired railway engineer who uses the Cumbria West Coast Line a fair amount. He travelled regularly through the tunnel and on one occasion last year notice the sound of the train’s wheels passing over the track sounded different, and in his view concerning. He did the same journey several times more recording the sound and reported his concerns to the rail authorities and Health and Safety Executive. Shortly afterwards the railway tunnel was closed until further notice.

Network Rail did not talk to him or thank him but announced their consultants had found an issue with the track bed. That issue is that the ground beneath the rail bed has for some considerable length (around 200 metres) has subsided into old mine workings below. The thickness of the bed holding the rails in place at points was less than 30 centimetres above an unsupported void.

The cavalier way the tunnel bed has been maintained or rather not maintained is concerning. Network Rail would not afford to pay for the pollution remedial work as it was not their problem rather it was the Mine Remediation Authority and the harbour’s. Now they say that the tunnel is mor than 180 years old and it requires maintenance. No mention of the pollution or if its remedial work will be included in the tunnel remedial works.

Present railway engineers state the minewater flooding the tunnel masked the problem and checks had not been conducted for some considerable time.

Whitehaven Bransty Tunnel.

In the autumn of 2025 several bore holes were put down through the base of the tunnel and others were sunk outside the tunnel (unknown locations). The depth of some of these exploration boreholes being more than 40 metres within the tunnel, while those outside would have been considerably deeper.

The Network Rail statement that the reason for this set of problems is the age of the tunnel (over 180 years) is poor as it was relined in 1950 and there should have been regular checks on the state of the tunnel for geological weaknesses and tunnel integrity on a regular basis. The fact that the line services Sellafield with wagon carried nuclear waste for recycling and treatment alone should have seen a modicum of extra care exercised.

If it was not for a local yachtsman and retired engineer this problem may have only been understood after a derailment or worse within the tunnel.